PROJECT OVERVIEW

This 300,000 sf office space for the Corporate Headquarters of Nintendo in Redmond, WA took 2310 pieces of steel and was erected in 10 days. The schedule was the driving force behind this project because Nintendo wanted the building to open 6 months earlier than the original schedule would allow. Apex worked with the General Contractor to make this happen and helped plan logistics of two tower cranes on the project that would support the accelerated schedule. Zoning and a comprehensive erection plan allowed Apex to use two tower cranes simultaneously with no jib or load line interference. Apex performed many scopes on this site including rebar, miscellaneous and tower crane erection.